Our new school has been built as part of the Bromsgrove Schools PFI Project.

 

 

 

 

                            

 

 

 

 

The plans were drawn and in January 2006

the machines moved onto site.

 

 

 

 

 

 

 

 

 

In March 2006 the children visited the site and saw

the foundations of their classrooms.

 

 

 

 

 

 

 

By June 2006 the steel frame for the hall was in place

and the block work walls were growing fast.

 

 

 

 

A view of the back of the school in June 2006.

 

 

 

 

 

The concrete roof sections being lifted onto the

Key Stage 1 classrooms.

 

 

 

 

 

 

 

 

The children visited the site again in September 2006.

HBG worked closely with the school and involved staff and children in many learning opportunities.

 

  

 

 

 The project manager, Gordon McCartin, helping pupils to build the tallest tower.

 

 

 

 

 

 

By December 2006, the outdoor playground areas

had started to take shape.

 

 

 

   

 

 

The entrance at Grayshott Close was constructed.

 

 

 

 

 

In December 2006, the coloured render was put on the hall and front of the building.

 

 

 

 

 

December 2006 view into the central courtyard from the roof.

 

 

  

  

 

Mrs Dixon's office in January 2007.

 

 

 

 

The hall is nearly ready for the sports flooring.

 

 

 

 

 

It is February 2007 and the car park is being made.

 

 

 

 

March 2007 - Nearly ready to move in.

 

 